General Category => General Computing/Macintosh => Topic started by: pongajim on October 01, 2016, 05:52:42 AM

Title: 28 day period limit?
Post by: pongajim on October 01, 2016, 05:52:42 AM
Newby here; last time I ran a version of this program was back in 2011 or 2012 with Stu I think?
Anyway I can't find the rationale for not seeing more than 28 days on the chart or how to see more than 28 days. I really need to see 6 dos or a year or 10 years if I scroll. The Davis software (win) does this very nicely so why not here?
Title: Re: 28 day period limit?
Post by: Felix on October 01, 2016, 12:51:51 PM
Custom graphs let you anchor data and then select a period (month--which goes to 31 days or a full year). Never tried more than a year so I don't know if that is possible.


Or maybe you're talking about custom graphs with scrolling data selected? In that case, you're correct, the max period is 28 days. I seem to remember that was brought up once and warranted a place in the queue of things to look at/consider for future enhancements.